Construction
The construction began
as soon as the snow melted, at the end of April 2007. The excavation and concrete
work were completed in two weeks. Next, I spent
a few days welding and painting the support columns. The floor
system was built in one week and then I spent a couple of days milling the wall
package. With the help of two additional
men and a construction lift, all of the walls were up within one week.
The roof took two weeks to frame, insulate, trim, and dry in with Ice & Water Shield.
In mid-July, the construction rate slowed down while we waited for the
subcontractors to finish their work and for materials to arrive.
By the end of August, the exterior was complete, the windows were in, and the
metal roof was on. During September, the electrical system, hydronic heating
system, and concrete slab were finished. The interior was drywalled during October.
Interior finishing, trim carpentry, and painting began in November and
my Folks moved in just before Christmas. The entire construction process took
just under 8 months.